Client Charter Status Achievement For June 2013
{arijdatatable bPaginate="true" asStripClasses="stat_odd,stat_even"}
| No. | Client Charter | No. of Received | No. of Processed | Achievement Percentage |
|---|---|---|---|---|
| 1 | Investigate and response to every complaint received within 3 days | 15 | 15 | 100% |
| 2 |
Appraisal for design approval of certificated machinery :
|
62 501 |
60 501 |
97% 100% |
| 3 | Approval for registration of Safety and Health Officer (SHO) for any complete application within 30 days | 37 | 37 | 100% |
| 4 | Approval for Competent Person of Hygiene Indusrty within 30 days | 162 | 14 | 9% |
| 5 | Approval for extension of Certificate of Fitness for unfired pressure vessel / steam boiler within 60 days | 7 | 6 | 86% |
| 6 | Processing and approval for application of Permission to Install and Operate a bulk storage installation within 15 days | 64 | 46 | 72% |
| 7 | Approval for Permission To Install (PTI) a pipelines within 14 days | 3 | 2 | 67% |
| 8 | Approval for Permission To Operate (PTO) a pipelines within 10 days | 10 | 8 | 80% |
| 9 | To conduct inspection and hydrostatic test on pipeline within 14 days | 1 | 1 | 100% |
| 10 | To commence forensic investigation after receiving notification of accident / incident at work places within 48 hours | 2 | 2 | 100% |
| 11 | Preparation of preliminary investigation report to the top management from the date of investigation within two (2) days | 2 | 2 | 100% |
| 12 | Approval for registration of Occupational Health Doctor (OHD) within 30 days | 22 | 22 | 100% |
| 13 | Response to each application to conduct talk/lecture and exhibition on occupational safety and health | 4 | 4 | 100% |
| 14 | To produce receipt for every payment transaction over the counter payment within 10 minutes | 155 | 155 | 100% |
{/arijdatatable}