Client Charter Status Achievement For March 2014

pdf  Client Charter Achievement for March 2014

 {arijdatatable bPaginate="false" asStripClasses="stat_odd,stat_even" bLength="25"}

No.Client CharterNo. of ReceivedNo. of ProcessedAchievement Percentage
1 Investigate and response to every complaint received within 3 days 7 7  100%
2

Appraisal for design approval of certificated machinery
i.  Steam Boiler within 60 days
ii. Unfired Pressure Vessel within 20 days

 

72
604

 

72
604

 

100%
100%

3 Approval for registration of Safety and Health Officer (SHO) for any complete application within 30 days 69  69 100%
4 Approval for Competent Person of Hygiene Indusrty within 30 days 72 64 89%
5 Approval for extension of Certificate of Fitness for unfired pressure vessel / steam boiler within 60 days 13 5  38%
6 Processing and approval for application of Permission to Install and Operate a bulk storage installation within 15 days  44 38  86%
7 Approval for Permission To Install (PTI) a pipelines within 14 days  4 4 100%
8 Approval for Permission To Operate (PTO) a pipelines within 10 days  5 5 100%
9 To conduct inspection and hydrostatic test on pipeline within 14 days  1 1 100%
10 To commence forensic investigation after receiving notification of accident / incident at work places within 48 hours 3 3 100%
11 Preparation of preliminary investigation report to the top management from the date of investigation within two (2) days 3 3 100%
12 Approval for registration of Occupational Health Doctor (OHD) within 30 days  15 15 100%
13 Response to each application to conduct talk/lecture and exhibition on occupational safety and health 4 4 100%
14 To produce receipt for every payment transaction over the counter payment within 10 minutes  145 145 100%

{/arijdatatable}

Print Email