Breadcumb Caption
  • Archive Statistics
  • 2014
  • Client Charter Status Achievement For August 2014
Breadcumb Caption
  • Archive Statistics
  • 2014
  • Client Charter Status Achievement For August 2014

Client Charter Status Achievement For August 2014

pdf  Client Charter Achievement for August 2014

{arijdatatable bPaginate="false" asStripClasses="stat_odd,stat_even" bLength="25"}

No.Client CharterNo. of ReceivedNo. of ProcessedAchievement Percentage
1 Investigate and response to every complaint received within 3 days  19 19 100%
2

Appraisal for design approval of certificated machinery
i.  Steam Boiler within 60 days
ii. Unfired Pressure Vessel within 20 days

 

57
686

 

57
686

 

100%
100%

3 Approval for registration of Safety and Health Officer (SHO) for any complete application within 30 days 135 135 100%
4 Approval for Competent Person of Hygiene Indusrty within 30 days 77  59 77%
5 Approval for extension of Certificate of Fitness for unfired pressure vessel / steam boiler within 60 days  10 5 50%
6 Processing and approval for application of Permission to Install and Operate a bulk storage installation within 15 days  28 38 135%
7 Approval for Permission To Install (PTI) a pipelines within 14 days 4 5 120%
8 Approval for Permission To Operate (PTO) a pipelines within 10 days  7 7 100%
9 To conduct inspection and hydrostatic test on pipeline within 14 days  2 2 100%
10 To commence forensic investigation after receiving notification of accident / incident at work places within 48 hours  2 2 100%
11 Preparation of preliminary investigation report to the top management from the date of investigation within two (2) days 2 2 100%
12 Approval for registration of Occupational Health Doctor (OHD) within 30 days  19 19 100%
13 Response to each application to conduct talk/lecture and exhibition on occupational safety and health  7 7 100%
14 To produce receipt for every payment transaction over the counter payment within 10 minutes  127 127 100%

{/arijdatatable}

Print Email