Client Charter Status Achievement For January 2017
pdf Client Charter Achievement for January 2017
{arijdatatable bPaginate="false" asStripClasses="stat_odd,stat_even" }
No. | Client Charter | No. of Received | No. of Processed | Achievement Percentage |
---|---|---|---|---|
1 |
Design appraisal of certificated machinery according to the:
i. Steam Boiler within 45 working days
ii. Unfired Pressure Vessel within 20 working days
|
44
646
|
44
609
|
100%
94%
|
2 | Process the application for registration of Safety and Health Officer (SHO) according to the requirements within 30 working days |
115 |
98 |
85% |
3 | Approval for extension of Certificate of Fitness for unfired pressure vessel / steam boiler within 60 days | 0 | 0 | 0% |
4 | Processing and approval for application of Permission to Install and Operate a bulk storage installation within 15 days | 40 | 40 | 100% |
5 | Approval for Permission To Install (PTI) a pipelines within 14 days | 1 | 1 | 100% |
6 | Approval for Permission To Operate (PTO) a pipelines within 10 days | 8 | 8 | 100% |
7 | To process a new application or renewal of a competent person to carry out Industrial Hygiene work within 30 working days after receiving a complete application | 142 | 142 | 100% |
8 | To process a new application or renewal of a assessor within 30 working days after receiving a complete application | 9 | 9 | 100% |
9 | To provide technical input and expertise in chemical management issues to internal staff and other agencies within 7 days | 12 | 12 | 100% |
10 | Approval for registration of Occupational Health Doctor (OHD) within 30 days | 16 | 16 | 100% |
11 | Investigate and response to every complaint received to department within 3 working days | 3 | 3 | 100% |
12 | Response to each complete application to conduct talk/lecture and exibition on Occupational Safety and Health within 7 working days | 0 | 0 | 0% |
13 | To commence forensic engineering investigation within 48 hours after receiving notification on an accident or incident | 2 | 2 | 100% |
14 | To produce receipt for every payment transaction over the counter payment within 10 minutes | 81 | 81 | 100% |
{/arijdatatable}